For a dive school and shop that teaches in its own deep pool.

Scuba and freediving training centre. District CMUO.
By right: allowed without a hearing. By permit: needs the permit named.
Layout Click a room to see its measurements
Dimensions are from the survey model. Verify on site.
Tinted on the plan.
| No. | Room | Used as | Area |
|---|---|---|---|
| G11 | PoolTraining in deep waterBasin not surveyed | Training in deep water | 479 SF (44.5 m²) |
| G10 | Pool courtyardWalled pool deck | Walled pool deck | 1,228 SF (114.1 m²) |
| G01 | Main hall, frontShop | Shop | 502 SF (46.6 m²) |
| G07 | Rear roomWorkshop: gear, fill station | Workshop: gear, fill station | 305 SF (28.3 m²) |
| G08 | Back roomWorkshop | Workshop | 225 SF (20.9 m²) |
| G14 | Covered garageTanks and vansOutline assumed | Tanks and vans | 492 SF (45.7 m²) |
| U01 | Front officeClassroom and offices | Classroom and offices | 407 SF (37.8 m²) |
The written answer on how a business that uses the open-air pool is classified. No duration is published for this letter. Source
For the fit-out and any change of use. The city: “All tenant improvements require building permits.” Source
A new operator applies in its own name. Plans and a Pool/Spa Data Sheet go to the department if anything is built, remodelled or the equipment is changed. Source
Required at a pool where a direct fee is charged for pool use. Source
A pool under 300 linear feet of wall needs one accessible entry, “either a pool lift or a sloped entry”; for an existing pool, “to the extent that it is readily achievable”. Source
The department lists an operational permit for compressed gas. Ask the Bureau of Fire Prevention whether a breathing-air fill station needs one. Source
Before any work on the pool shell, deck, enclosure, plumbing, filtration or heater.
For installing or replacing a pool heater. Source
Under 50 occupants an assembly use is classed as business (Group B). At 50 or more it becomes Group A, which changes the exiting and fire protection requirements.
With any permitted alteration. Below the state valuation threshold, path-of-travel upgrades are capped at 20% of the adjusted construction cost; above it, a fully accessible path of travel is required. Source
Fire permits are not transferable. Any change of operator or use needs a new permit. Source
For installing or changing a business sign or awning. Painted or vinyl lettering applied directly to windows, doors or the facade is exempt. Source
Ask the SFPUC before the pool is emptied whether this permit applies. Source
Before signing: the Certificate of Final Completion and Occupancy, older permits and job cards that are not online. $0.10 per page; up to 15 days. Source
Cost band: medium.
Shop fixtures and a classroom indoors. The cost sits in the pool: its pump, filter and heater need inspecting, and a pool lift or a new heater would add to it.
Time band: 1 to 3 months.
No hearing for the shop. The open items are the Zoning Administrator’s letter and the pool permit with its inspection. Remodelling the pool means plan review and 3 to 6 months.
What to check for this use before committing.
The shop and indoor classes are by right. Teaching in the open-air pool is by permit: it needs a Zoning Administrator letter, because district uses must be within an enclosed building with named exceptions, and a Health Department Permit to Operate.
San Francisco's Health Department says: “All public pool and spa operators must have a valid Permit to Operate”. A new operator needs their own permit, and state rules count swim school and club pools as public pools.